Bitcoin miner MARA borrows $185 million for Ohio power plant

MARA Holdings is raising $185 million in bonds to help fund its $1.5 billion purchase of an Ohio gas plant, as the bitcoin miner sells coins and borrows to reposition itself as a supplier of power and computing for artificial intelligence.

By Himanshu Sakre

Published · 5 min read

Bitcoin miner MARA Holdings is borrowing $185 million to help fund its roughly $1.5 billion purchase of an Ohio gas plant, a deal that pushes the company further into supplying power for artificial intelligence.

A subsidiary, MARA USA Corporation, opened the sale of 8.750 percent senior secured notes due 2032 on November 16, according to a filing with the US Securities and Exchange Commission. CryptoBriefing reported that the notes priced two days later. They are being sold privately, to large investors, and have not been registered for public trading.

What MARA is buying

MARA USA agreed on April 29, 2026 to buy Long Ridge Energy and Power from FTAI Infrastructure. The filing lists a base price of about $1.5 billion, before adjustments. At the center of the deal is a natural gas plant in Hannibal, Ohio, rated at 505 megawatts, with more than 1,600 acres of land and its own grid connection. CoinDesk described the plant as 485 megawatts, a smaller figure than the company's own disclosures use.

FTAI Infrastructure, the seller, is handing over a plant that already runs, already burns gas, and already feeds the grid. That matters. Building new power from scratch can take years and runs into local objections. MARA is buying a site that works today, with room to grow computing next to it.

How the debt is structured

The new notes join $600 million of matching notes Long Ridge already has outstanding under an indenture dated February 19, 2025. Together, the $785 million carries about $68.7 million in interest a year. MARA said it will use the money, with cash on hand, to close the acquisition, repay part of Long Ridge's existing debt, and pay fees. The remaining cost is backstopped by a bridge loan from Barclays.

An 8.750 percent coupon is a high rate to carry. It signals that lenders still see risk in a bitcoin miner buying a power plant, even a profitable one. MARA is betting the plant's cash flow, and the AI tenants it hopes to land, will cover the bill with room to spare.

A miner that wants to sell power

Buying the plant is the clearest sign yet that MARA wants to sell electricity and computing capacity, not only mine coins. Fred Thiel, the company's chief executive, called Long Ridge a "highly efficient, contracted energy platform" when the deal was announced in April. A power company that happens to mine bitcoin. That is roughly where MARA is heading.

MARA plans to build a data center campus next to the plant, placing computing right beside its own generation. The company says the site has drawn interest from AI and IT tenants. It has named no tenants. No public leases, either. CryptoBriefing reported the deal would raise MARA's operating power capacity by about 65 percent, to roughly 2.2 gigawatts. The plant is expected to add about $144 million in yearly adjusted earnings, based on its second-half 2025 results.

Why miners want power plants

Bitcoin mining and AI computing run on the same thing, cheap and steady electricity. Mining pay shrank after the 2024 halving cut the block reward, so the cost of power now decides which miners earn a profit. Owning a plant lets MARA sell that power two ways, to its own machines and to outside AI customers, rather than buying it at market rates.

A pure miner lives and dies by the bitcoin price. A company that owns power and rents it to AI firms earns steadier cash, the kind lenders and shareholders tend to reward with a higher value. Whether MARA can sign those AI leases is the open question, and the reason the plan is not yet proven.

The bitcoin sales behind it

To get here, MARA has been selling bitcoin. It sold 13,597 coins after the third quarter at an average of $81,039 each, raising about $1.1 billion, and put $750 million toward loans backed by those coins. BTC Newz reported those sales earlier this month. The repayment released 17,477 coins that had been pledged as collateral. Some of the loans had helped fund the Long Ridge deal in the first place.

That trade cuts both ways. Selling coins near $81,000 and borrowing at 8.750 percent is an expensive way to chase demand that is not yet signed. Companies that only hold bitcoin on their books have had a hard autumn too, after the price fell below its summer lows. One of them, Strategy, now holds coins worth less than it paid, as BTC Newz has reported.

What to watch

MARA's bond sale will not close unless the purchase does. The company is targeting a close around November 27, 2026, after federal energy regulators cleared the deal on November 5. Two things are still open. MARA has not said how much of Long Ridge's debt the new cash will retire. It has also not signed the AI tenants it needs to fill the campus. Until those leases are public, the plan rests on demand the company says it has seen but has not shown.

Frequently asked

What is MARA buying with the $185 million?

MARA's subsidiary is raising $185 million in senior secured notes to help pay for Long Ridge Energy and Power, a natural gas plant in Hannibal, Ohio. The whole deal is worth about $1.5 billion. MARA plans to turn the site into a data center campus for artificial intelligence, run on the plant's own electricity.

Why is MARA selling bitcoin?

MARA sold 13,597 bitcoin after the third quarter, about $1.1 billion worth, mainly to repay loans secured against its coins. Those loans had helped fund the Long Ridge purchase. The company says it is not abandoning bitcoin but moving toward owning power and selling computing, where it sees steadier demand from AI firms.

When will the Long Ridge deal close?

MARA is targeting a close around November 27, 2026. Federal energy regulators approved the deal on November 5. The bond sale is tied to the purchase and will complete only if the acquisition does. MARA has not confirmed the final split between cash and assumed debt, or named any tenants for the planned AI campus.

Sources, and what is behind them

  1. MARA Holdings Form 8-K: Long Ridge $185 million senior secured notes offering, U.S. Securities and Exchange Commission (November 16, 2026)Filing
  2. MARA Holdings raises $185M in debt to fund Ohio power plant acquisition, CryptoBriefing (November 18, 2026)Press report
  3. Bitcoin miner MARA to acquire Long Ridge in $1.5 billion Ohio gas plant deal, The Block (April 30, 2026)Press report